WESLEY CHAPEL, FL — The number that stands out in Pasco County's proposed Old Pasco Road development agreement is $7.14 million.

But understanding what that money would buy — and when drivers might actually see the results — requires looking beyond the price tag.

Under a proposed agreement between Pasco County and Meritage Homes of Florida, the homebuilder would design, permit and construct a four-lane section of Old Pasco Road extending from the Coyote Way/Sedgeway Boulevard area north to approximately Old Mill Road.

Pasco County, rather than the developer, would ultimately reimburse the cost of the road improvements in cash. County staff estimated that reimbursement at $7,140,000.

At the same time, Meritage is connected to a residential project allowing 106 townhomes on approximately 18.36 acres near Old Pasco Road and Hadlock Drive.

That combination — new housing, public road money and a developer constructing the infrastructure — makes the agreement particularly relevant for residents trying to understand how growth and transportation improvements are being coordinated along one of Wesley Chapel's developing corridors.

And there is another important detail: the townhomes would not necessarily have to wait for the widened road.

Why Meritage Homes is involved in a public road project

The arrangement traces back to the Old Pasco Road Master Planned Unit Development.

Pasco County approved a rezoning in 2025 allowing the 106-townhome development. Conditions associated with that approval required a development agreement addressing improvements to Old Pasco Road.

The resulting proposal uses a public-private structure: Meritage would handle the design, permitting and construction of the road segment, while Pasco County would reimburse the company for the qualifying road work.

The Pasco County Planning Commission considered the development agreement in October and recommended approval to the Board of County Commissioners.

That recommendation did not approve the agreement. The final decision belongs to county commissioners.

INSIDE THE $7.14 MILLION PROPOSALProposed Old Pasco Road Development Agreement • PDE27-0036MERITAGE HOMESDesign • Permit • Constructthe road improvementsPASCO COUNTYCash reimbursement$7.14M ESTIMATEPROPOSED ROAD RESULTOld Pasco Road widened from 2 lanes to 4Coyote / Sedgeway Boulevard → approximately Old Mill RoadProposal pending Pasco County Commission action • Not yet approved

What would actually be built?

The proposed typical road section is considerably more than simply adding two traffic lanes.

Plans call for four 12-foot travel lanes, a 22-foot center median, two 5-foot bicycle lanes, a 6-foot sidewalk along the east side and a 12-foot multi-use path along the west side.

Final engineering details would still be determined during the permitting process.

The segment would begin just north of the Coyote Way/Sedgeway Boulevard intersection and continue to approximately Old Mill Road.

That matters because another section immediately to the south is already part of an ongoing widening effort. The proposed agreement would extend four-lane capacity farther north rather than create an isolated road improvement.

The question residents may care about most: Which comes first, the homes or the road?

Under the proposed agreement, there is no simple "road first, homes second" requirement.

The agreement provides that building permits, plats and certificates of occupancy for the residential development cannot be withheld solely because the road design and construction are still underway, provided Meritage remains in compliance with the agreement.

In practical terms, housing construction and road construction could proceed in parallel.

That distinction is important. Approval of the agreement would establish deadlines for the road work. It would not mean the four-lane road must be finished before residents begin moving into the new development.

How long could the road improvements take?

The proposed agreement establishes several milestones rather than an immediate construction date.

After the agreement becomes effective, Meritage would have to begin the design process within 90 days and apply for the required permits within 12 months.

Construction would then have to be completed within 24 months after the necessary permits are obtained.

WHAT HAPPENS NEXT?Timeline under the proposed development agreementDEC. 8Public hearing90 DAYSDesign begins12 MONTHSPermit applications24 MONTHSAfter permits: construction completeDeadlines begin only if the agreement is approved, executed and recorded.

The schedule means drivers should not interpret a Dec. 8 approval — if commissioners approve the agreement — as the beginning of road construction. Design and permitting come first.

Another responsibility falls on Pasco County

The agreement also separates responsibility for the road itself from land needed for drainage.

According to the proposed terms, Pasco County already controls the roadway right of way needed for the improvements, but additional property would be needed for drainage ponds.

The county would be responsible for obtaining that property from the Pasco County School District within 90 days after the agreement takes effect, without passing that acquisition cost to the developer.

That creates another dependency in the project's schedule beyond Meritage's design and permitting work.

What the proposal does — and does not — mean

Several distinctions are important as the Dec. 8 hearing approaches.

It does mean: Pasco County is considering a mechanism to extend four-lane capacity farther north on Old Pasco Road while a nearby residential project moves forward.

It does mean: Meritage would take responsibility for designing, permitting and constructing that segment under county oversight.

It does mean: The county expects to reimburse the road work, currently estimated at $7.14 million.

It does not mean: The agreement has already been approved.

It does not mean: Construction begins Dec. 8.

It does not mean: The 106 townhomes must wait until the road is completed.

And it should not be confused with other Old Pasco Road transportation projects planned or underway elsewhere along the corridor.

Why the Nov. 17 vote never happened

County commissioners had been scheduled to consider the agreement during their Nov. 17 meeting in Dade City.

They never reached a decision on its merits.

County staff told commissioners that the required public notice for the development agreement had been published incorrectly and requested that the hearing be continued.

The procedural problem moved consideration of the agreement to Dec. 8.

The delay therefore should not be interpreted as commissioners rejecting or approving the road deal. It remains pending.

The next decision comes Dec. 8

The Pasco County Board of County Commissioners is scheduled to consider the Old Pasco Road Development Agreement during its public-hearing session beginning at 1:30 p.m. Tuesday, Dec. 8, 2026.

The meeting will be held at West Pasco Government Center, 8731 Citizens Drive, New Port Richey, FL 34654.

The case is PDE27-0036 — Old Pasco Road Development Agreement, Meritage Homes of Florida, LLC.

Members of the public can attend the hearing and provide comment before commissioners act on the proposal. County meetings are also broadcast through Pasco County's online video services and local government-access television channels.

Commissioners could approve the agreement, modify it, deny it or continue consideration again.

Until they act, the $7.14 million road agreement remains exactly what its name says: a proposal.

NºSources
1Pasco County Board of County Commissioners — Nov. 17, 2026 agenda and meeting record, PDE27-0036
2Pasco County Planning Commission — Oct. 22, 2026 meeting record, Old Pasco Road Development Agreement
3Pasco County Planning, Development and Economic Growth — PDE27-0036
4Pasco County FY 2027 Capital Improvement Plan materials